GROUP: |
Building |
TYPE: |
Grading |
SUB-TYPE: |
Commercial |
PRIMARY USE: |
(70) Grading - Hillside |
WORK DESCRIPTION: |
DRAINAGE CHANNEL/STREAMBED RESTORATION |
PERMIT ISSUED: |
Yes |
PERMIT ISSUE DATE: |
09/17/2012 |
ISSUING OFFICE: |
Metro |
CURRENT STATUS: |
Permit Finaled |
CURRENT STATUS DATE: |
10/16/2014 |
|
|
Submitted |
11/15/2011 |
APPLICANT |
Assigned to Plan Check Engineer |
11/17/2011 |
FREDERICK WONG |
Corrections Issued |
11/17/2011 |
FREDERICK WONG |
Plan Check Approved |
09/17/2012 |
FRED WONG |
Issued |
09/17/2012 |
LADBS |
Permit Finaled |
10/16/2014 |
BRIAN OLSON |
Excavation more than 5-ft deep |
Cleared |
02/01/2012 |
CALOSHA APPROVED |
Drainage to Storm Drain |
Cleared |
09/14/2012 |
PHONG NGUYEN |
Eng Process Fee Ord 176,300 |
Cleared |
09/14/2012 |
PHONG NGUYEN |
Roof/Waste drainage to street |
Cleared |
09/14/2012 |
PHONG NGUYEN |
Watercourse |
Cleared |
09/14/2012 |
PHONG NGUYEN |
Work Adjacent to Public Way |
Cleared |
09/14/2012 |
PHONG NGUYEN |
Grading Pre-Inspection |
Cleared |
09/17/2012 |
FRED WONG |
|